Kit Section |
Hours |
Status |
Empennage
Sec. 6: Vertical Stabilizer
Sec. 7: Rudder VS and Rudder Log
Sec. 8: Horizontal Stabilizer
Sec. 9: Elevator HS and Elevator Log
Sec. 10: Tailcone
Sec. 11: Emp Attach
Sec 12: Fairings Tailcone etc. Log
SB 08-6-1 |
30
31
61
67
99
24
29
5 |
Completed 2/22/08
Completed 3/6/2008
Completed 4/5/2008
Completed 5/10/2008
Completed 6/10/2008
Completed 6/29/08
Completed 7/11/08
Completed (347 hrs total) |
Wings (Quick Build)
Sec. 16,18: Misc
Sec. 18: Fuel Tank
Sec. 19: Stall Warning System
Sec. 20: Bottom Wing Skins
Sec. 23: Aileron Actuation
Sec. 24: Wing Tip
OP-36: Wing Tip Lighting
OP-37: Aileron Trim
Wing Log |
6
16
7
59
26
10
12
9 |
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed (144 hrs total) |
Fuselage (Standard Build)
Sec. 25: Mid Fuse Bulkhead
Sec. 26: Mid Fuse Ribs
Sec. 27: Firewall
Sec. 28: Fwd Fuse Ribs
Sec. 29: Side Skins
Sec. 30: Step Installation
Sec. 31: Upper Fwd Fuse
Sec. 32: Tailcone Attach
Sec. 33: Baggage Area
Sec. 34: Baggage Door
Fuselage Log 1 |
24
44
18
62
92
8
30
14
46
14 |
Completed 10/17/08
Completed 11/15/08
Completed 11/20/08
Completed 12/21/08
Completed 02/01/09
Completed
Completed
Completed
Completed 03/22/09
Completed |
Sec. 35: Access Covers
Sec. 36: Brakes
Sec. 37: Fuel System
Sec. 38: Rudder Pedals
Sec. 39: Control System
Sec. 40: Flap System
Sec. 41: Upper Fwd Fuse
Sec. 42: Rear Seats
Sec. 43: Cabin Cover
Sec. 44: Wing Attach
Fuselage Log 2
Cabin Cover Modifications |
42
7
22
20
22
14
38
8
122
10
|
Completed and painted
Completed 4/12/09
Completed
Completed 5/17/09
Completed 5/24/09
Completed 6/4/09
Completed 6/26/09 (riveting defered)
Completed 6/5/09
Finally completed 9/17/09
Completed for now
(657 hrs fuselage, 1,144 hrs project) |
Finish Kit
Sec. 45: Cabin Doors/Windows
Sec. 46: Engine Mount/Landing Gear
Sec. 44b: Wing Attach part 2
Finish Kit Log1
|
173
31
41
|
Completed 12/13/09. Yeah!
Completed 12/26/09.
Completed 6/18/10
|
Sec. 47: Spinner and Cowl
Sec. 48: Gear Fairings Wheel Door
Sec. 49: Seats and Belts
Sec. 50: Cabin Heat
Finish Kit Log2
|
154
121
15
1 |
Completed 6/3/10
Completed 2/26/10.
Completed 6/25/10
Completed
(536 hrs finish kit, 1,680 hrs project) |
Firewall Forward
Sec. FF1: Engine Installation
Sec. FF2: Cowl Baffle
Sec. FF3: Control Cables
Sec. FF4: Fuel System
Sec. FF5: Oil System
Sec. FF6: Exhaust System
EIS Wiring and Sensors
Firewall Forward Kit Log |
35
85
12
36
5
14
26 |
Completed 3/27/2010
Completed 8/8/10
Completed 8/27/2010
Completed 9/26/2010
Completed 9/9/2010
Completed 10/3/2010
Completed 8/15/2010
(178 hrs Firewall Fwd kit, 1,904 hrs project) |
Panel & Avionics
Panel
Flight Systems
Pitot Static and Auto Pilot
Radio Systems
System Test
Antennas
ELT
Avionics Log |
15
36
7
26
5
12
7 |
Completed 10/31/10
Completed 11/1/10
Completed 10/17/10
Completed 11/22/10
Completed 12/9/10
Completed 12/7/10
Completed 12/13/10
(108 hrs Avionics, 2,012 hrs project) |
Finishing Touches
Windshield Install
Carpet
Seats and Harnesses
Finishing Touches Log
|
52
6
7 |
Completed
Completed
Completed (2,078 hrs project total) |
Airport Assembly
The Big Move
Wing Attach
PowerPlant and Propeller
Empennage Attach
Prep for DAR and First Flight
At the Airport Log
|
10
52
8
22
12 |
Completed 2/11/2011
Completed 3/20/11
Completed 3/26/11
Completed 3/29/11
Its Done!!!!!! 2,182 hrs in 1,150 days |
Painting
Design, Preparation, Paint
|
- |
See left Navbar for Painting |