I like building my airplane,
'cause it doesn't remind me of anything.

skeleton.jpg

Feb 2008: I estimate 1800 hrs to build the airplane. I am going to try to keep a pace of 10 hrs per week. Estimated completion is 3.5 years, July of 2011. By that time, I should be at the top of the Falcon Field 7 year waiting list for a hanger. 118 people ahead of me on the list.

Feb 2009: 736 hours completed in first year. Estimate 2000 hrs at completion. There are 92 people ahead on the hanger list.

Feb 2010: 694 hours completed in second year. 1,430 hrs on the project so far. Estimate 2150 hrs at completion. There are 57 people ahead on the hanger list.

 

    **** Click on blue links for detailed building logs ****

Kit Section

Hours

Status

Empennage
    Sec. 6: Vertical Stabilizer
    Sec. 7: Rudder VS and Rudder Log
    Sec. 8: Horizontal Stabilizer
    Sec. 9: Elevator HS and Elevator Log
    Sec. 10: Tailcone
    Sec. 11: Emp Attach
    Sec 12: Fairings Tailcone etc. Log
    SB 08-6-1

 
30
31
61
67
99
24
29
5

 
Completed 2/22/08
Completed 3/6/2008
Completed 4/5/2008
Completed 5/10/2008
Completed 6/10/2008
Completed 6/29/08
Completed 7/11/08
Completed (347 hrs total)

Wings (Quick Build)
    Sec. 16,18: Misc
    Sec. 18: Fuel Tank
    Sec. 19: Stall Warning System
    Sec. 20: Bottom Wing Skins
    Sec. 23: Aileron Actuation
    Sec. 24: Wing Tip
    OP-36: Wing Tip Lighting
    OP-37: Aileron Trim
    Wing Log

6
16
7
59
26
10
12
9

Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed (144 hrs total)

Fuselage (Standard Build)
    Sec. 25: Mid Fuse Bulkhead
    Sec. 26: Mid Fuse Ribs
    Sec. 27: Firewall
    Sec. 28: Fwd Fuse Ribs
    Sec. 29: Side Skins
    Sec. 30: Step Installation
    Sec. 31: Upper Fwd Fuse
    Sec. 32: Tailcone Attach
    Sec. 33: Baggage Area
    Sec. 34: Baggage Door
    Fuselage Log 1

24
44
18
62
92
8
30
14
46
14

Completed 10/17/08
Completed 11/15/08
Completed 11/20/08
Completed 12/21/08
Completed 02/01/09
Completed
Completed
Completed
Completed 03/22/09
Completed

    Sec. 35: Access Covers
    Sec. 36: Brakes
    Sec. 37: Fuel System
    Sec. 38: Rudder Pedals
    Sec. 39: Control System
    Sec. 40: Flap System
    Sec. 41: Upper Fwd Fuse
    Sec. 42: Rear Seats
    Sec. 43: Cabin Cover
    Sec. 44: Wing Attach
    Fuselage Log 2
    Cabin Cover Modifications

42
7
22
20
22
14
38
8
122
10
 

Completed and painted
Completed 4/12/09
Completed
Completed 5/17/09
Completed 5/24/09
Completed 6/4/09
Completed 6/26/09 (riveting defered)
Completed 6/5/09
Finally completed 9/17/09
Completed for now
(657 hrs fuselage, 1,144 hrs project)

Finish Kit
    Sec. 45: Cabin Doors/Windows
    Sec. 46: Engine Mount/Landing Gear
    Sec. 44b: Wing Attach part 2
   Finish Kit Log1

173
31
41

Completed 12/13/09. Yeah!
Completed 12/26/09.
Completed 6/18/10

    Sec. 47: Spinner and Cowl
    Sec. 48: Gear Fairings Wheel Door
    Sec. 49: Seats and Belts
    Sec. 50: Cabin Heat
   Finish Kit Log2

154
121
15
1

Completed 6/3/10
Completed 2/26/10.
Completed 6/25/10
Completed
(536 hrs finish kit, 1,680 hrs project)

Firewall Forward
    Sec. FF1: Engine Installation
    Sec. FF2: Cowl Baffle
    Sec. FF3: Control Cables
    Sec. FF4: Fuel System
    Sec. FF5: Oil System
    Sec. FF6: Exhaust System
    EIS Wiring and Sensors
   Firewall Forward Kit Log

35
40
-
-
-
-
10

Completed 3/27/10
<====== working here now
-
-
-
-
-

Panel & Electrical
   Avionics
   Sec. 41 Instrument Panel Rivet
   Sec. 45 Windshield Attach

-
-
-

-
-
-

Airport Assembly
   Sec. 32 Empennage Attach
   Sec. 44 Wing Attach
   Ground Test

-

-

 

 

 

AzCloudFlyer
Last update 19Jul2010